University Medical Centre of Geneva (steps 5 and 6)

Local authorities

Types of mandate

Full mandate (SIA): preliminary project, project and execution

Dates

Final building permit: 2007 / 2010
Investment credit approval: May 2007 / 2011
Opening of the construction site: April 2009 / November 2011
Handover of buildings: November 2016

Technical
informations

CMU 5: 33,611 m2 of GFA, 140,800 m3 SIA
CMU 6: 21,290 m2 of GFA, 81,300 m3 SIA
Total: 54,901 m2 of GFA, 222,100 m3 SIA

Location

Geneva

Collaborators

S. Chambat, J.-B. Meyrier, P. Revillard,
V. Paclet, W. Marsura, A. Piazza, M. Delapierre,
P. Vaz, J. Debljovic, A. Belladon, G. Genecand

 

Simplicity serving a multifunctional complex

On seven basement levels and nine current floors, the allocations spread over several tens of thousands of square metres show the impressive heterogeneity of a complex site dedicated to teaching and advanced medical research. 

The complex brings together (as a non-exhaustive and non-hierarchical list of functions) the French-speaking school of pharmacy, the university dental medicine clinic, numerous laboratories, areas dedicated to clinical development and investigation, interfaculty work spaces, a pet house and a simulation centre.

Despite its highly focused design and ubiquitous technology, the building’s layout remains flexible, modular and reversible. This adaptability, which was requested at the design stage by the contractors and the Project Owner, is intended to simplify any future modifications.

The new CMU marks an important milestone in the history of the hospital district. It does so with as much strength as serenity as a measure of its successful integration, without trampling on the past and with an openness to future opportunities.

One of the challenges during the construction phase was to manage the nuisance caused by the work on the occupied site. It is obviously critical to ensure discretion during such a project, when the existing premises are high-precision laboratories. 

MORE INFORMATION

25’000m2

dedicated to research 
and laboratories

60

nursery places 
on the 3rd floor of the CMU

100

dentists’ offices 
at the University Clinic of Dental Medicine (CUMD)