Types of mandate
Project, execution file and architectural
management (implementation: Implenia AG as general contractor)
Dates
Building permit: November 2004
Construction site finished: March 2007
Technical
informations
959 m2 de SBP, 5’330 m3 SIA
Location
Cologny
Collaborators
L. Bionda, N. Favre, S. Fiore
Project
Following an invitation-based preliminary design contest, we were asked to develop a residency project for an embassy to the International Organisations in Geneva. This building is designed for use both as a reception area and as accommodation for an ambassador’s family during his or her stay in Geneva. It is set up on two levels, in front of the lake, on a massive foundation which follows the slope of the land and offers several openings.